Contact
We think you might be interested in Bilfinger %s website.
Otherwise select the country you are interested in here.
+

Steam pipeline Agrana Stärke (DLAS) including tie-in and conversion work EVZ 2 power plant Dürnrohr

Customer:

EVN Wärmekraftwerke GmbH

Location:
Austria
Markets:
Heat storageEnergy
Scope:

At the Dürnrohr power plant site, the existing 17 bar steam system was adapted in preparation for the supply of a new steam pipeline to be installed within the heat node in EVZ 2.
Bilfinger Bohr- und Rohrtechnik's scope of delivery included the integration into the existing steam pipework systems
Steam behind MDU DN 300
after the turbine extraction DN 350
Existing pipeline, 17 bar distributor DN 400
50 bar pipe to MDU DN 200
Detailed planning, prefabrication of the pipework, delivery, installation and assembly of the new pipework including support structure and operating platform, insulation of the pipework and commissioning and trial operation.

Services:
ProjectProfessionalsEngineeringMechanical
captcha
Your message for
captcha