We performed an overhaul of a 50MW steam turbine generator at a concentrated solar plant in Spain. The complete overhaul was executed under tight COVID-19 restrictions, and delivered 4 days ahead of the planned schedule.
Project | Major Overhaul Steam Turbine Generator 50MW |
Client | ContourGlobal |
Name of facility | Palma 1 |
Type of facility | Thermal Solar Power |
Industry | Solar |
OEM | Nuevo Pignone |
Site location | Palma del Rio, Spain |
Duration | Outage 6 weeks, preparation 3 months |
Role | Main contractor |
Contract type | Lumpsum (full-scope major overhaul) |