

Spain
We performed an overhaul of a 50MW steam turbine generator at a concentrated solar plant in Spain. The complete overhaul was executed under tight COVID-19 restrictions, and delivered 4 days ahead of the planned schedule.
| Project | Major Overhaul Steam Turbine Generator 50MW |
| Client | ContourGlobal |
| Name of facility | Palma 1 |
| Type of facility | Thermal Solar Power |
| Industry | Solar |
| OEM | Nuevo Pignone |
| Site location | Palma del Rio, Spain |
| Duration | Outage 6 weeks, preparation 3 months |
| Role | Main contractor |
| Contract type | Lumpsum (full-scope major overhaul) |
We partnered with the client from start to end. As the main contractor we were responsible for full outage preparation, execution and commissioning, implementing our proven outage project approach. Our risk-based approach enabled the team to proactively steer on risks and implement mitigating actions.
We delivered the following services: