Outage of a 50MW Concentrated Solar Plant

Customer:

ContourGlobal

Location:

Spain

The Netherlands
Markets:
Energy TransitionEnergy
Scope:

We performed an overhaul of a 50MW steam turbine generator at a concentrated solar plant in Spain. The complete overhaul was executed under tight COVID-19 restrictions, and delivered 4 days ahead of the planned schedule. 

 
Fast facts
ProjectMajor Overhaul Steam Turbine Generator 50MW
ClientContourGlobal
Name of facilityPalma 1
Type of facilityThermal Solar Power
IndustrySolar
OEMNuevo Pignone
Site locationPalma del Rio, Spain
DurationOutage 6 weeks, preparation 3 months
RoleMain contractor
Contract typeLumpsum (full-scope major overhaul)

 

Services:
SustainabilityTurnaround
  • We partnered with the client from start to end.
  • As the main contractor we were responsible for full outage preparation, execution and commissioning. 
  • Implementing our proven outage project approach.
  • Risk-based approach enabled the team to proactively steer on risks and implement mitigating actions.

 

Delivering the following services:

  • Commissioning & technical consultancy
  • Turnaround/Outage Management (turnkey)
  • Commissioning & technical consultancy
  • Major Overhaul LP & HP turbines incl. valves
  • Disassembly and assembly of all equipment
  • Inspection of Generator
  • Inspection of Gearbox
  • Electrical & Instrumentation
  • Reverse engineering & fabrication of spare parts
  • On-site balancing
  • Logistics

     

    Client benefits
     
    • Safe and high-quality delivery
    • Single point of contact for complete outage scope
    • Project delivered 4 days ahead of planned schedule