3 New Pumps to Increase Pumping Station Capacity

Customer:

Watershed Noorderzijlvest

Location:

Schaphalsterzijl, Netherlands

The Netherlands
Markets:
Adjacent Industries
Scope:

Bilfinger produced and installed three new Stork OVOP 160 pumps to increase pumping station capacity, including fish-friendly fish passage, at the pumping station Schaphalsterzijl in the Netherlands.

  • New pumps including drivetrain
  • 3x electric motors, 220 kW
  • 3x gearboxes
  • 3x frequency converters
  • New electrical installation including instrumentation
  • Innovative 100% fish-friendly fish passage
  • Commissioning & Site Acceptance Tests
Technical data:
  • Type: 3x Stork OVOP 160
  • Capacity: van 3 m3/min to 235 m3/min 
  • Head: van 0.13 m to 0.85 m
Execution: 
  • Design: 2019
  • Execution: 2020
Services:
MechanicalEI&CRotating Equipment